The first phase of a major scheme to improve Whitby’s public spaces and road network is set to begin on Monday after being delayed due to the moorland fires.
The junction at the A171 New Bridge with Spital Bridge will benefit from a £500,000 upgrade to improve safety for road users and pedestrians.
The works will form part of the £2.3 million Whitby harbourside public realm project, funded by the Whitby Town Deal, which aims to improve the area around the swing bridge for the benefit of residents and visitors.
The work had been due to start this week but was postponed following local concerns about access for emergency service vehicles working on the Langdale Moor fire.
The work will now begin on Monday 8 September and is expected to be completed within 12 weeks.
It will involve installing new traffic lights, amendments to islands and kerb lines, and the resurfacing of the new junction. There will be four new places clearly signed for pedestrians to cross, including on the A171 in one movement.
Executive member for highways and transport, Cllr Malcolm Taylor, said:
“This major upgrade is seen by many to be much needed as the new signals will make life much easier for those emerging from the side roads, and will improve the crossing places for pedestrians.
“We listened to public feedback from the consultation, which showed significant public support for the plans, with most feedback coming from Whitby residents.
“This scheme is the first phase of our wider vision for the popular coastal town, with plans for the harbourside set to come to fruition next year.”
During a public consultation for the improvement scheme in late 2023, 64 per cent of people were in favour.
When the swing bridge is closed to traffic, all vehicles travelling between the east side of Whitby and the town centre need to use A171 New Bridge and Spital Bridge junction. The right turn at this location is a difficult manoeuvre in its current layout.
Cllr Neil Swannick, who represents the Whitby Streonshalh division on North Yorkshire Council, said:
“I strongly support the major improvements to this key junction, which was mirrored by most people who shared their views in the consultation.
“Although the works will inevitably cause short term disruption at the junction, there will be huge benefits from the crossing points, and they will provide a safer route for the many students who make their way to Whitby School on the west side of New Bridge.”
Most of the works will take place during the daytime between 7am and 7pm. However, during the first week, works will be 7pm to 2am, and for the second and last week, they will be daytime and evening.
The on-site team will help in managing access to properties and businesses. However, there may be periods when vehicle access will not be possible.
Access for pedestrians will be maintained, but it may be necessary to use temporary barriered walkways.
The next phase of the public realm improvements is due to begin in the spring of next year.


Future of Scarborough Town Hall Hangs in Balance Ahead of Crucial Property Decision
The Scarborough Buildings North Yorkshire Council Could Buy and Sell
Yorkshire Coast Camper Van Consultation Outcome
Scarborough Teacher Takes On London Marathon To Support YMCA
Scarborough and Whitby Harbours Hope To Be Turbo-Charged By Renewables Funding
NFU and Police Warning After Rising Attacks On Sheep In Yorkshire
Woman Fined After Her Waste Was Fly-Tipped In East Riding Countryside
Scarborough Athletic Held In Six Pointer But Stay In Top Seven
"Pathetic"- Whitby Town Crumble To Defeat To Ten Men
Brid Rugby Table Topping Bid Ends In Thriller
Bridlington Town Held Despite Batty Belter
Pickering Town Back To Winning Ways







Comments
Add a comment